TAP: More than 20 pct of Project's Pipeline Work in Greece Completed

TAP: More than 20 pct of Project's Pipeline Work in Greece Completed

Out of the approximately 550 km of pipeline scheduled to be built on Greek soil, the Trans Adriatic Pipeline’s (TAP) contractors have already lowered 119 km of pipeline -or more than 20 percent- into the trench, the company said on Tuesday in a press release detailing the progress made. 
Ten months after the inauguration ceremony held in May 2016, construction has significantly progressed in two of the three northern Greek prefectures to be traversed by the pipeline: Eastern Macedonia-Thrace and Central Macedonia.
As of end-March 2017, contractors have received 66 percent of the total 32,000 line pipes to be used for the construction of the pipeline’s Greek section, cleared and graded 260 km of the project’s route, strung 217 km of pipeline, welded 184 km of the mainline and opened 154 km of trench. 
 
 
ANA-MPA
Cookies Preferences
Choose Type of Cookies You Accept Using


These cookies are required for the website to run and cannot be switched off. Such cookie are only set in response to actions made by you such as language, currency, login session, privacy preferences. You can set your browser to block these cookies but our site may not work then.


These cookies allow us to measure visitors traffic and see traffic sources by collecting information in data sets. They also help us understand which products and actions are more popular than others.


These cookies are usually set by our marketing and advertising partners. They may be used by them to build a profile of your interest and later show you relevant ads. If you do not allow these cookies you will not experience targeted ads for your interests.